Orange Line Transformation Weekly Progress Update: September 23 – 29
Updated on September 29, 2023
![two crew members working on floor inside with orange line train in the background](https://cdn.mbta.com/sites/default/files/styles/max_2600x2600/public/media/2023-09/2023-09-29-olt-weekly-update.png?itok=WG6C4dXN)
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Orange Line Transformation projects will improve safety, reliability, and access for Orange Line riders and the surrounding communities.
Last week, work continued on the following projects:
- Wellington Yard and Maintenance Facility Updates – 96% complete
- Traction Power Substations – 78% complete
- Orange Line Signal Upgrades – 30% complete