Orange Line Transformation Weekly Progress Update: September 9 – 15
Updated on September 15, 2023

Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Orange Line Transformation projects will improve safety, reliability, and access for Orange Line riders and the surrounding communities.
Last week, work continued on the following projects:
- Wellington Yard and Maintenance Facility Updates – 96% complete
- Traction Power Substations – 78% complete
- Orange Line Signal Upgrades – 30% complete