Orange Line Transformation Weekly Progress Update: February 25 – March 3
Updated on March 3, 2023
![worker in reflective vest standing in front of two laptops looking at a sheet with a large diagram on it](https://cdn.mbta.com/sites/default/files/styles/max_2600x2600/public/media/2023-03/2023-03-03-olt-weekly-update.png?itok=8Dj9t5xc)
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
OLT projects will improve safety, reliability, and access for Orange Line riders and the surrounding communities.
Last week, work continued on the following projects:
- Wellington Yard and Maintenance Facility Updates – 95% complete
- Traction Power Substations – 78% complete
- Orange Line Signal Upgrades – 28% complete