Codman Yard Construction Update | September 14 – October 4, 2024
Updated on September 24, 2024

Construction activities are ongoing on the Codman Yard Expansion and Improvements project. Over the next three weeks, crews will work on track installation, duct banks, and the utility bridge.
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Construction Progress Update
- Crews will continue work on track installation, duct banks for electrical conduits and manholes, and the utility bridge during weekdays and Saturdays, 7 AM – 3 PM.
- There is no 24-hour work scheduled.
- Crews will not work on Sundays.